The tasks necessary to producs product in 8 hours to meet the demand of 480 units are:
Task Predecessor Time (seconds)
A - 20
B A 30
C B 25
D - 50
E C,D 40
F C 30
1.) The required cycle time (in minutes) is?
2.) What is the number of