The tasks necessary to producs product in 8 hours to meet the demand of 480 units are:

Task Predecessor Time (seconds)
A – 20
B A 30
C B 25
D – 50
E C,D 40
F C 30
1.) The required cycle time (in minutes) is?

2.) What is the number of workstations needed to meet the schedule?

3.) The assembly line’s efficienct is?

4.) The highest efficiency that you could achieve under this line is?