The tasks necessary to producs product in 8 hours to meet the demand of 480 units are:

Task Predecessor Time (seconds)
A – 20
B A 30
C B 25
D – 50
E C,D 40
F C 30
1.) The required cycle time (in minutes) is?

2.) What is the number of workstations needed to meet the schedule?

3.) The assembly line’s efficienct is?

4.) The highest efficiency that you could achieve under this line is?

Expert Answer


https://d2vlcm61l7u1fs.cloudfront.net/media%2F939%2F93958dd8-8ae6-4ba1-85ee-e2f399676afa%2FphpEw6UY8.png

https://d2vlcm61l7u1fs.cloudfront.net/media%2F79e%2F79e28073-15eb-4477-a5a6-d3a063761b8f%2Fphpll12XM.png

Leave a Reply

Your email address will not be published. Required fields are marked *

Related Post

(Solved) : Help Implh Enum False 0 True Typedef Enum Name Birthdate Gpa Personfield Define Maxbuff 10 Q27014442 . . . .(Solved) : Help Implh Enum False 0 True Typedef Enum Name Birthdate Gpa Personfield Define Maxbuff 10 Q27014442 . . . .

<p>Help!</p><p>impl.h</p><p>enum {FALSE=0, TRUE};<br/>typedef enum {NAME, BIRTHDATE, GPA} PersonField;</p><p>#define MAXBUFF 1024 // maximum size of string buffer for inputfile</p><p>typedef struct person_t Person;<br/>typedef Person *PersonPtr;<br/>typedef char *Cstring;</p><p>typedef struct { // basic date