Given the following information for a project, determine thecritical path.

Activity

Immediate Processor

Activity Time (days)

A

6

B

8

C

A,B

5

D

B

4

E

C

7

F

C,D

3

G

D

6

H

E,F,G

5

B-C-E-H

A-C-E-H

A-B-C-H

NONE OF THE ABOVE

Expert Answer


Ans: B-C-E-H

Explanation: The critical path is the longest path that takes tocomplete

B-C-E-H = 8+5+7+5 = 25