Assume Takt Time Product 20 Seconds Customer Order 10 000 Units Lead Time 3 Days Assuming Q34261550

Assume the TAKT-TIME for a product is 20 seconds and yourcustomer order is 10,000 units and the Lead time is 3 days.Assuming the company works 24 hours/day, are you able to satisfyyour customer’s demand in both time and quantity?

Expert Answer


TAKT-TIME is the maximum time in which a product can beproduced in such a way that it is satisfactory forcustomer

Given that , TAKT-Time = 20 secs

Now, Total Demand = 10,000 units

Total Time taken = 20sec *10,000 = 200000 secs = 2.31days

Now total lead time given = 3 days.

Hence, we will be able to satisfy both customers demandin quantity and quality

OR

PayPal Gateway not configured

OR

PayPal Gateway not configured

Leave a Reply

Your email address will not be published. Required fields are marked *

Related Post

(Answered) : Which of the following best describes the Earned Value Management (EVM Concept of internal planning? A) Replanning the remining(Answered) : Which of the following best describes the Earned Value Management (EVM Concept of internal planning? A) Replanning the remining

Which of the following best describes the Earned Value Management (EVM Concept of internal planning? A) Replanning the remining baseline to an over target baseling (OTB). B) The contractor's realignment