Assume the TAKT-TIME for a product is 20 seconds and yourcustomer order is 10,000 units and the Lead time is 3 days.Assuming the company works 24 hours/day, are you able to satisfyyour customer’s demand in both time and quantity?
Expert Answer
TAKT-TIME is the maximum time in which a product can beproduced in such a way that it is satisfactory forcustomer
Given that , TAKT-Time = 20 secs
Now, Total Demand = 10,000 units
Total Time taken = 20sec *10,000 = 200000 secs = 2.31days
Now total lead time given = 3 days.
Hence, we will be able to satisfy both customers demandin quantity and quality