Course Solutions Uncategorized (Answered) : The predecessor information and activity time estimates in months are as follows: Activity Immediate Predecessor Optimistic T

(Answered) : The predecessor information and activity time estimates in months are as follows: Activity Immediate Predecessor Optimistic T

The predecessor information and activity time estimates in months are as follows:

Activity Immediate Predecessor Optimistic Time Most likely Pessimistic Time Expected Time Variance

A None 2 4 6

B None 1 4 7

C A 2 2 2

D B 1 7 10

E D 2 4 6

F E 1 2 3

G C 3 4 17

H E, G 3 7 11

I E 8 9 10

J F, H 4 5 6

K I 1 1 1

Which of the following is the critical path?

ACGHJ

BDEHJ

BDEFJ

What is the duration?

What is the slack time for activity F?

Expert Answer


Solution :

Critical Path : BDEHJ

Duraiton : 26.5

Slack for F : 5

https://d2vlcm61l7u1fs.cloudfront.net/media%2F2be%2F2be9cbd8-1c69-42c6-bc79-906438821745%2FphpmTDVGx.png

Leave a Reply

Your email address will not be published. Required fields are marked *

Related Post

(Solved) : 1 1 Constant Time Takes Amount Time Regardless Input Size 2 0 Log N Logarithmic Time 3 0 N Q35220936 . . . .(Solved) : 1 1 Constant Time Takes Amount Time Regardless Input Size 2 0 Log N Logarithmic Time 3 0 N Q35220936 . . . .

<p><em><strong>What is the order of growth for the followingfunctions?<img alt="1. Θ(1)-constant time takes the same amount of time regardless of input size 2. 0(log n)-logarithmic time 3. 0(n)-linear time" src="https://media.cheggcdn.com/media%2F45f%2F45fbfc2d-4a43-442c-8bb8-e2b1a88313d7%2FphpjSOKkb.png"