QUESTION 5
Suppose there are four steps in a process with steps A and B are done in parallel. The output of A and B is assembled in step C followed by a quality check in step D. The capacities of steps A, B, C, and D are 20, 25, 14, and 45 units/day. What is the capacity of the process in units/hour?