*Answer question 41 using information on question37.

Question 37 1/1 pts A project has a cost estimate of $50 per week and is scheduled for completion in 10 weeks. The actual cost and earned value data are collected for the first 7 weeks. The actual costs are 50, 50, 60, 60, 50, 40, and 50. The earned values are: 50, 50, 55, 65, 45, 35, and 40. Please do the following: (a) evaluate its cost and schedule variances at the end of week 7, (b) calculate its cost, schedule and project performance indices at the end of week 7, (c) 