Exercise 8: Consider the following project time data (in days) and the network diagram. Activity Time A 12 B 20 C 24 D 12 E 18 F 18 G 28 H 20 D Dummy 4 a) Calculate the earliest and latest starting and finishing times and the slack values for all of the activities. b) Determine the critical path and the project completion time.
https://d2vlcm61l7u1fs.cloudfront.net/media%2Fa9f%2Fa9f152e0-b63b-4842-801e-919dab709e95%2FphpYdP8gq.png
(Answered) : Exercise 8: Consider the following project time data (in days) and the network diagram. Activity Time A 12 B 20 C 24 D 12 E 18 F 1