Exercise 6: The assembly of a product consists of eight tasks as given below. The company works 5 days per week in two shifts every day. Each shift is 9 hours and workers have 30 minute meal-break and two 15-minute tea breaks. The desired production rate is 1500 units/week. TaskTime (seconds)Immediate Predecessors 90 90 30 50 20 25 30 70 4 5,6 a) Calculate the maximum cycle time to achieve the desired production rate b) Draw the precedence diagram. c) Assign tasks to stations using the Ranked Positional Weight (RPW) technique assuming a cycle time of 150 seconds. d) Calculate