Refer to the following table:
Activity
Predecessor
Normal Time
Normal Cost
Crash Time
Crash Slope
A
–
4
30
3
10
B
–
7
60
5
70
C
A
1
80
1
N/A
D
B
4
40
2
20
E
B
5
110
2
50
F
C
5
90
2
200
G
D
2
60
1
30
H
E
2
70
1
40
I
F, G, H
2
140
2
0
Note: Crash time indicates the time it could be crashed to (e.g. A could be crashed to 3 units but not less than that)
While trying to crash project duration, an intermediate step had the following activity durations:
Activity
Intermediate time
A
4
B
5
C
1
D
3
E
4
F
5
G
2
H
1
I
2
Based on the above information, find the activity(activities) that will be selected next after this intermediate step. In addition, find the crash time (minimum project duration) and corresponding cost. (hint: continue the crash time calculation from the intermediate step provided above but note that you have final crash times provided in the first