Course Solutions Uncategorized (Answered) : Refer to the following table: Activity Predecessor Normal Time Normal Cost Crash Time Crash Slope A –

(Answered) : Refer to the following table: Activity Predecessor Normal Time Normal Cost Crash Time Crash Slope A –

Refer to the following table:

Activity

Predecessor

Normal Time

Normal Cost

Crash Time

Crash Slope

A

4

30

3

10

B

7

60

5

70

C

A

1

80

1

N/A

D

B

4

40

2

20

E

B

5

110

2

50

F

C

5

90

2

200

G

D

2

60

1

30

H

E

2

70

1

40

I

F, G, H

2

140

2

0

Note: Crash time indicates the time it could be crashed to (e.g. A could be crashed to 3 units but not less than that)

While trying to crash project duration, an intermediate step had the following activity durations:

Activity

Intermediate time

A

4

B

5

C

1

D

3

E

4

F

5

G

2

H

1

I

2

Based on the above information, find the activity(activities) that will be selected next after this intermediate step. In addition, find the crash time (minimum project duration) and corresponding cost. (hint: continue the crash time calculation from the intermediate step provided above but note that you have final crash times provided in the first

OR

PayPal Gateway not configured

OR

PayPal Gateway not configured

Leave a Reply

Your email address will not be published. Required fields are marked *