The tasks necessary to producs product in 8 hours to meet the demand of 480 units are:

Task Predecessor Time (seconds)
A – 20
B A 30
C B 25
D – 50
E C,D 40
F C 30
1.) The required cycle time (in minutes) is?

2.) What is the number of workstations needed to meet the schedule?

3.) The assembly line’s efficienct is?

4.) The highest efficiency that you could achieve under this line is?

Expert Answer


https://d2vlcm61l7u1fs.cloudfront.net/media%2F939%2F93958dd8-8ae6-4ba1-85ee-e2f399676afa%2FphpEw6UY8.png

https://d2vlcm61l7u1fs.cloudfront.net/media%2F79e%2F79e28073-15eb-4477-a5a6-d3a063761b8f%2Fphpll12XM.png

Leave a Reply

Your email address will not be published. Required fields are marked *

Related Post

(Solved) : C Programming Updated Create Program Calculate Employee S Monthly Gross Pay Follows Inputs Q28864008 . . . .(Solved) : C Programming Updated Create Program Calculate Employee S Monthly Gross Pay Follows Inputs Q28864008 . . . .

<p>This is for C# programming (updated)</p><p><strong>Create a program that will calculate employee’s monthlygross pay as follows:</strong></p><p>Inputs:</p><p>1)Name</p><p>2)Annual Salary</p><p>3)Monthly Sales</p><p>4)Keeps asking for additional inputs and creating the outputsuntil an empty name is