Course Solutions Uncategorized (Answered) : When using uncertainty in task times, the variance for completion time for the project is given by the sum of the variances for

(Answered) : When using uncertainty in task times, the variance for completion time for the project is given by the sum of the variances for

When using uncertainty in task times, the variance for completion time for the project is given by the sum of the variances for only those tasks that are on the critical path. (True/FAlse?)

Expert Answer


False

With the variability of the activity completion times, the original critical path analysis may not always be the actual critical path as per the project