(Answered) : When using uncertainty in task times, the variance for completion time for the project is given by the sum of the variances for

When using uncertainty in task times, the variance for completion time for the project is given by the sum of the variances for only those tasks that are on the critical path. (True/FAlse?)

Expert Answer


False

With the variability of the activity completion times, the original critical path analysis may not always be the actual critical path as per the project

Leave a Reply

Your email address will not be published. Required fields are marked *

Related Post

(Solved) : Please C Use Good Format Also Explanatations Confusing Code Would Appreciated 3 Implement Q27720030 . . . .(Solved) : Please C Use Good Format Also Explanatations Confusing Code Would Appreciated 3 Implement Q27720030 . . . .

<p>Please do this in C++ and use good format. Also someexplanatations for some confusing code would be appreciated.</p><p>(3) Implement the function getNumOfNonWSCharacters().getNumOfNonWSCharacters() has a constant string as a parameter andreturns