consider the following data for MRP. Develop the materials requirements plan for item C, D and E. you can use the empty table in page & for MPA calculations
MPA start
end time for item A , week 3 120, week 4 110
Bill of materials
End item A is made of 2 units of component C and 1 unit of subassembly D
Subassembly D is made of 1 unit of component E
MRP- related information for each item
Item C , Lead time 2 weeks, lot sizing POQ 2, Safety stock 30, On hand inventory 120, Scheduled
Receipts 120 in week 2
Item D , Lead time 1