Course Solutions Uncategorized (Answered) : consider the following data for MRP. Develop the materials requirements plan for item C, D and E. you can use the empty table in

(Answered) : consider the following data for MRP. Develop the materials requirements plan for item C, D and E. you can use the empty table in

consider the following data for MRP. Develop the materials requirements plan for item C, D and E. you can use the empty table in page & for MPA calculations

MPA start

end time for item A , week 3 120, week 4 110

Bill of materials

End item A is made of 2 units of component C and 1 unit of subassembly D

Subassembly D is made of 1 unit of component E

MRP- related information for each item

Item C , Lead time 2 weeks, lot sizing POQ 2, Safety stock 30, On hand inventory 120, Scheduled

Receipts 120 in week 2

Item D , Lead time 1