Course Solutions Uncategorized (Answered) : Ventaz Corp manufactures small windows for back yard sheds.​ Historically, its demand has ranged from 30 to 50 windows per day

(Answered) : Ventaz Corp manufactures small windows for back yard sheds.​ Historically, its demand has ranged from 30 to 50 windows per day

Ventaz Corp manufactures small windows for back yard sheds.​ Historically, its demand has ranged from 30 to 50 windows per day with an average of 41. Alex is one of the production workers and he works eight hours a​ day, five days a week. Each order is one window and each window takes 55 minutes.

What is the cycle time for an​ order?

A. 6.86 minutes per window

B12.5minutes per window

C.5minutes per window

D. 250minutes per window

Expert Answer


Cycle Time= 1/ Throughput rate

Throughput rate= Task/ Time

Task= 30+50= 80 windows

Time= 8*5(eight hours, five week) = 40

Throughput rate= 80/40=2

Cycle Time=1/2=0.5

Answer is C.5minutes per window

Leave a Reply

Your email address will not be published. Required fields are marked *

Related Post