What is the cycle time for an​ order?

A. 6.86 minutes per window

B12.5minutes per window

C.5minutes per window

D. 250minutes per window

Expert Answer


Cycle Time= 1/ Throughput rate

Throughput rate= Task/ Time

Task= 30+50= 80 windows

Time= 8*5(eight hours, five week) = 40

Throughput rate= 80/40=2

Cycle Time=1/2=0.5

Answer is C.5minutes per window

Leave a Reply

Your email address will not be published. Required fields are marked *

Related Post

(Answered) : Problem 4 15 Points Mikey W Smitty Emerging Rapper Getting Ready Cut First Cd Called Weste Q33067615(Answered) : Problem 4 15 Points Mikey W Smitty Emerging Rapper Getting Ready Cut First Cd Called Weste Q33067615

<br/><img src="https://media.cheggcdn.com/media%2F3f7%2F3f72d776-2ffb-4222-a4bc-710f4fb6225e%2Fimage.png" alt="PROBLEM 4 (15 points) Mikey W. Smitty, an emerging rapper, is getting ready to cut his first CD, called Western recording the CD is $5000 but copies are