Product A is made from components B and C. Item? B, in? turn, ismade from D and E. Item C also is an intermediate? item, made fromF and H.? Finally, intermediate item E is made from H and G. Notethat item H has two parents. The following are item lead?times:
|
Item |
A |
B |
C |
D |
E |
F |
G |
H |
|
Lead Time? (weeks) |
2 |
1 |
2 |
7 |
2 |
4 |
2 |
4 |
a. What lead time? (in weeks) is needed torespond to a customer order for product? A, assuming no existinginventories or scheduled? receipts?
?
weeks. ?(Enter your response as aninteger?.)