Q6:Draw activity on- (AOA) Network by using( DUMMY) Task?

ACTVITY PREDECESSOR OPTEMISTIC TIME(DAYS) MOST LIKL PESSIMISTIC TIME(DAYS)
A _ 2 6 10
B A 3 6 9
C A 4 8 12
D B 5 7 9
E C 6 8 10
F B,C 3 6 9
G D,E 2 5 8
H C 3 7 11

Expert Answer 


A solution will be send to your mail shortly . . . .

Leave a Reply

Your email address will not be published. Required fields are marked *

Related Post

Question 3 Following Project Draw Aon Network Determining Critical Path Earliest Completio Q34314141Question 3 Following Project Draw Aon Network Determining Critical Path Earliest Completio Q34314141

<br/><img src="https://media.cheggcdn.com/media%2Feef%2Feef17012-4b34-4382-9b4d-a0d934db31d0%2Fimage.png" alt="QUESTION 3: For the following project draw the AON network determining the critical path and the earliest completion time of the project. Activity Predecessor B, C D, E