Course Solutions Uncategorized (Answered) : Q6 Draw Activity Aoa Network Using Dummy Task Actvity Predecessor Optemistic Time Days Lik Q30638109

(Answered) : Q6 Draw Activity Aoa Network Using Dummy Task Actvity Predecessor Optemistic Time Days Lik Q30638109

Q6:Draw activity on- (AOA) Network by using( DUMMY) Task?

ACTVITY PREDECESSOR OPTEMISTIC TIME(DAYS) MOST LIKL PESSIMISTIC TIME(DAYS)
A _ 2 6 10
B A 3 6 9
C A 4 8 12
D B 5 7 9
E C 6 8 10
F B,C 3 6 9
G D,E 2 5 8
H C 3 7 11

Expert Answer 


A solution will be send to your mail shortly . . . .

Leave a Reply

Your email address will not be published. Required fields are marked *

Related Post