Xcel Electronics manufactures small robotic toys for children.They have received the following set of six jobs that needs to beprocessed through two work-centers at their manufacturingfacility. The sequence of operations is to first produce themodules in the first work-center and then assemble the toys intheir assembly line (second work-center). Processing time at eachof the work-centers is shown in thetable.
Job
Work-Center 1(hours)
Work-Center 2(hours)
Upper QQ
1
3
Upper RR
10
12
Upper SS
8
7
Upper TT
11
9
Upper UU
4
6
Upper VV
2
13
Scheduled OrderJob1(Q, T, U, R, V, S)2(Q, T, U, R, V, S)3(Q, T, U, R, V, S)4(Q, T, U, R, V, S)5(Q, T, U, R, V, S)6(Q, T, U, R, V, S)
b) For the