a) The Acme Baking Company (ABC) produces custom cakes.
b) Each cake takes exactly one day to create.
c) Only one cake may be baked each day.
d) Each cake provides a profit to ABC.
e) Each cake must be delivered at the end of a specifiedday.
f) The cake may be baked on, or at any time prior to, thedelivery day
For a ten-day period, ABC has the following order list:
Order #Delivery DayProfit1470242036204440510706210788082209370109801146012370134801486015940163501732018510019109020390
1. Outline a greedy strategy you can use to schedule the cakeproduction for the next 10 days.
2. What is the schedule produced using this strategy?
3. What is the total profit?