Sixsigma Green belt test
54. The Define Stage of a DMAIC process is intended toA. Agree between Green Belt and Sponsor, the scope andbusiness objectives of projectB. Identify the solution of the problemC. Identify the cause of the problemD. Not communicate to management55. What is the process of Cycle Efficiency (PCE) for aprocess with the following parameters: WIP =600 units; Value Add(VA) time = 5hrs; and Exit Rate = 20 units/hr?A. 16.7%B. 6%C. 10%D. 4%56. Why should we assess process capabilityA. Enable comparison of actual performance and the customerspecific limitB. We don’t really need to compare process capability if wealready know