Section B Q6 Figure 51 Shows Pert Diagram Project Durations Weeks 30 3 5 12 8 10 15 3 6 11 Q34210451

Hi please do A,B,C as all related with working out please

SECTION B Q6. Figure 5.1 shows a PERT diagram for a project with durations in weeks 30 3,5,12 8,10,15 3,6,11 10 70 0 100 3,5,7 4,5,12 4,8,15 4,6,10 4,5,9 50 3,7,9 5,8,15 5,9,13 Figure 5.1- PERT Chart a) Calculate the expected time and the variance for each task. Expected time [o+4m pl/6 Variance of activity time [(p - o)/6) (6 marks) b) For each parallel path, calculate the variance, the standard deviation, the standardized score, the probability of completion of each path in 24 weeks, and the probability that 