Question 3 options:
PS.72 A toy manufacturer wants to produce and sell an upscaletoy NASCAR racer. Eight steps or tasks are required to assemblethese high-end toy cars. Daily demand is 64 units and there are 600minutes available each day to meet this production quota.
Task Req’d Time (in minutes) PredecessorA7NoneB4NoneC5A, BD9CE4DF4EG8EH7F, G
What is the total time (in minutes) to produce one car?
What is the takt time (in minutes) for this productionline? (Display your answer to a one decimalplace.)
What is the theoretical minimum number of workstations requiredfor this production line? (Round up your answer tothe nearest whole number.)
Which task should you assign to workstation 1?
Which