PS.74 Bell computer is planning to launch a new high-end server.Nine steps or tasks are required to assemble this computer. Dailydemand is expected to be 88 units and there are three 8-hour shiftsavailable each day to meet this production quota.
Task Req’d Time (in minutes) PredecessorA12NoneB15AC5BD6BE16AF4C,DG7FH14EI8G,H
A. What is the total time, in minutes, to produce oneserver?
B. What is the takt time (in minutes) for this production line?(Round your answer to twodecimal places.)
C. What is the theoretical minimum number of workstationsrequired for this production line? (Round up youranswer to the nearest whole number.)
D. After assigning task A to workstation 1, which task (ortasks) should