Project Management –  Resource Leveling Exercise

  1. Using the figure, perform resource leveling. Assume that eachtask can be performed independently of the other tasks.
  2. Referring again to this figure, perform resource-limitedscheduling. Assume that only three workers are available at anygiven time. What is the new completion date for the project?

Task 1-2 workersTask 2-1 workerTask 3-0 workersTask 4-2 workersTask 5-1 workerTask 6-3 workersDay12345678910Available Workers6664233433

Expert Answer


Tasks 1, 4 and 6 required 2, 2 and 3 workers respectively.Therefore, none of these activities can be scheduled simultaneouslywith any of these activities. So, these tasks are scheduledsequentially. However, tasks 2 and 5 require 1 worker each. So,task 2