The Mini-Mobile produces a scanning processor for a scanningdevice that captures “Big-Data” in a text, voice or video format.To manufacture this processor efficiently, they have divided themanufacturing process into six different tasks (see the tablebelow). Demand for this processor is estimated to be 4,600 unitsper week (40-hours a week). List of tasks, tasktime, and theirsequences are shownbelow:
Task
Task Time
(seconds)
Predecessors
A
20
−
B
28
A
C
12
A
D
14
A
E
12
B, C
F
28
D, E
a) Given the demand, the cycle time for the production of thenew processor = ? seconds (round your response to one decimalplace).
b) The theoretical minimum number of work stations = ? (roundyour response up to the next whole number).
c) Using the