A Master Production Schedule (MPS) which was developed from theMRP technique for inventory planning and control, indicates that acompany to produce and supply tires to 800 vehicles in 40 weeksperiod. The bill of materials (BOM) provides for 5 tires pervehicle. The inventory status is at 1500 hundred tires and theremaining tires need to be produced; Draw the MaterialsRequirements Plan (MRP) and calculate the following: (a) Calculatethe Gross requirements (number) in terms of the total tires neededto be produced and supplied. (b) Calculate the net requirements(number) in terms of the total tires needed to be produced andsupplied. (c) What will be