The manager of a crew that installs carpeting has tracked thecrew’s output over the past several weeks, obtaining thesefigures:
WeekCrew SizeYards Installed13103227234102455856726753
a. Compute the labor productivity for each of theweeks. (Round your answers to 2 decimalplaces.)
WeekCrew sizeLabor productivity
(Yards/Person)132234455667
b. Which crew size works best?
A crew of seems to work best.
Expert Answer
A. Labor productivity = Number of yards installed / crewsize
Week 1 = 103 / 3 = 34.33
Week 2 = 72 / 2 = 36
Week 3 = 102 / 4 = 25.5
Week 4 = 58 / 5 = 11.6
Week 5 = 72 / 6 = 12
Week 6 = 53 / 7