Which of the following is not a Material PlanningSystem/Technique?

a) MRP

b) MRP-II

c) JIT

d) ERP

e) None of the Above

Expert Answer


The correct answer is (c) JIT.

JIT stands for Just-In-Time which is just a lean principle. Thisis not a Material Planning System/Technique.

Leave a Reply

Your email address will not be published. Required fields are marked *

Related Post

(Solved) : 2 Define Implement Test Complex Class Least Two Constructors B Destructor C Several Method Q27720521 . . . .(Solved) : 2 Define Implement Test Complex Class Least Two Constructors B Destructor C Several Method Q27720521 . . . .

<br/><img src="https://media.cheggcdn.com/media%2F2ae%2F2ae198b4-107f-4489-a03d-1ed5cfd452cc%2Fimage" alt="2. Define, implement and test a Complex class, which has: (a) At least two constructors. (b) A destructor. (c) Several Methods with functionality as described below: . Returns