Explain Difference Responsive Responsible Terms Sourcing Bidder Responsive Responsible Imp Q34237912

Explain the difference between being responsive andresponsible in terms of sourcing. Can a bidder be responsive, butnot responsible? Why is it so important that procurement andcontracting officers ensure bidders are responsible, and not justresponsive, when analyzing bids and proposals duringsourcing?

Expert Answer


answer-

A bid is responsive if the bid meets all of the requirements ofthe bidding documents or solicitation.A contractor, businessentity, or individual who has submitted a bid or proposal thatfully conforms in all material respects to the Invitation for Bids(IFB)/Request for Proposals (RFP) and all of its requirements,including all form and substance (NGIP).

A bidder is responsible if they are

OR

PayPal Gateway not configured

OR

PayPal Gateway not configured

Leave a Reply

Your email address will not be published. Required fields are marked *

Related Post

(Solved) : Answer Chegg Wrong Error Code Error Test Satmul2 2147483648 0x80000000 Failed Gives 214748 Q26367838 . . . .(Solved) : Answer Chegg Wrong Error Code Error Test Satmul2 2147483648 0x80000000 Failed Gives 214748 Q26367838 . . . .

<p>The other answer on Chegg is wrong with this error code:</p><p>"ERROR: Test satMul2(-2147483648[0x80000000]) failed...</p><p>...Gives -2147483648[0x80000000]. Should be 0[0x0]"</p><p>please give the correct answer in C</p><p>Tmin = 0x7FFFFFFF</p><p>Tmax = 0x80000000</p><p>/*</p><p>* satMul2 -