Evaluate the network diagram using PERT andcalculate the probability in completing in 15 days- Using Z table
A- B – C
Start End
D -E – F
Given that estimated time of completion Te(ABC)=19 with standarddeviation=3 and Te(DEF)=21 with standarddeviation=5
Expert Answer
For path ABC, z Value = (15-19)/3 = -1.333
P(z<=-1.333) = NORMSDIST(-1.333) = 0.0912
For path DEF, z Value = (15-21)/5 = -1.2
P(z<=-1.2) = NORMSDIST(-1.2) = 0.1151
Probability of completing in 15 days = 0.0912*0.1151 =0.0105