Development of Version 2.0 of a particular accounting softwareproduct is being considered by Jose Noguera’s technology firm inBaton Rouge. The activities necessary for the completion of thisproject are listed in the following table:
Activity Normal Time (weeks) Crash Time(weeks) Normal Cost Total Cost withCrashing Immediate Predecessor(s)
A 4 3 $2,100 $2,750 –
B 2 1 $2,200 $2,800 –
C 3 3 $600 $600 –
D 8 4 $2,300 $2,620 A
E 6 3 $1,000 $1,450 B
F 3 2 $3,200 $4,600 C
G 4 2 $1,600 $2,200 D, E
c) For reducing the duration of the project by one week, theactivity that should be crashed first is activity D
The cost of the project based on the