Consider the following information about a project network.
Activity
Time (weeks)
Predecessors
A
2
—
B
3
—
C
2
A
D
4
A, B
E
4
C
F
3
C
G
5
D, E
H
2
F, G
What is the completion time for this project (inweeks)?
A.
25
B.
15
C.
20
D.
13
Consider the following information about a project network.
Activity
Time (weeks)
Predecessors
A
2
—
B
3
—
C
2
A
D
4
A, B
E
4
C
F
3
C
G
5
D, E
H
2
F, G
What is the critical path in this network?
A.
Critical Path is A, C, E, G, H
B.
Critical Path is B, D, G, H
C.
Critical Path is A, C, F, H
D.
Critical Path is B, D, C, F, H
We know the following about a project. We also know only onecritical path exits. Times are in weeks.
Activity
Optimistic
Most Likely
Pessimistic
Critical?
A
1
2
3
Yes
B
2
3
4
No
C
1
2
3
Yes
D
2
4
6
No
E
1
4
7
No
F
1
2
9
Yes
G
3
4
11
No
H
1
2
3
Yes
What is the expected completion time for theproject?
A.
9 weeks
B.
12 weeks
C.
23 weeks
D.
46 weeks