C&A Furniture uses a four-step process to make its famouswood table. They work an 8-hour day. The milling machine requires asetup time of 30 minutes to make table tops and a changeover timeof 30 minutes to make table stands. Process – Processing time(minutes) Milling table top – 10 Milling table stand – 5 Assembly -15 Finishing – 20 What is the total setup time (in minutes) in thisprocess?
A. 30
B. 15
C. 60
D. 45
Expert Answer
Setup time is total time which a machine takes to change fromone product to another. Changeover time is also a type of set uptime setup time.
Thus set