Which of the following terms refers to that which “Pulls” production to the constraint for processing? (the answer is C, could you let me know the reasons in details? tks.)
a. Drum
b. Buffer
c. Rope
d. Kanban
Expert Answer
Ans:
Option C
Rope
Drum buffer control is a planning and control system that regulates the flow of materials at the bottleneck in a productive system. The drum sets the pace for resources , buffer eliminates any disruption and rope works for subordinating the resources and decisions according to the activity of the drum. This means rope controls the production rate of the bottleneck and pulls