When is it useful to compare baseline, interim, and actual plans in a single view?

Expert Answer


Baseline:- Baseline Plans are the plans for the entire project and can be used to evaluate the progress of the entire proect; Interim Plans are the plans for the various tasks It is a set of current project data that you save after the project begins. It saves only two kinds of information the current start dates and finish dates for tasks.

In a single view we can easily compare baseline, interim and actual plans by changing the formatting of items. We can