vorites Tools Help ▼ Page ▼ Safety ▼ Tools Problem 12-2 The following table lists the components needed to assemble an end item, lead times, and quantities on hand. End B 5 2 Amount on hand 0 127 27 1330 4 0 a. If 20 units of the end item are to be assembled, how many additional units of E are needed? (Hint You don’t need to develop an MRP plan to determine this.) Additional units 135 b. An order for the end item is scheduled to be shipped at the stat of week 16. What is the latest week