The predecessor information and activity time estimates in months are as follows:

Activity Immediate Predecessor Optimistic Time Most likely Pessimistic Time Expected Time Variance

A None 2 4 6

B None 1 4 7

C A 2 2 2

D B 1 7 10

E D 2 4 6

F E 1 2 3

G C 3 4 17

H E, G 3 7 11

I E 8 9 10

J F, H 4 5 6

K I 1 1 1

Which of the following is the critical path?

ACGHJ

BDEHJ

BDEFJ

What is the duration?

What is the slack time for activity F?

Expert Answer


Solution :

Critical Path : BDEHJ

Duraiton : 26.5

Slack for F : 5
https://d2vlcm61l7u1fs.cloudfront.net/media%2F2be%2F2be9cbd8-1c69-42c6-bc79-906438821745%2FphpmTDVGx.png

Leave a Reply

Your email address will not be published. Required fields are marked *

Related Post

(Solved) : 2 20 Pts Running Johnson S Algorithnm Similar Problem Started Class Different Graph G 6 6 Q33200621 . . . .(Solved) : 2 20 Pts Running Johnson S Algorithnm Similar Problem Started Class Different Graph G 6 6 Q33200621 . . . .

<p><img alt="2. (20 pts) Running Johnsons Algorithnm This is similar to the problem you started in class, but with a different graph G 6 -6 2 7" src="../../../media.cheggcdn.com/media/fca/fca526c2-ae75-4152-879d-214a0908103f/php3q8EnR.png" style="height:387px;width:685px;" aria-describedby="d3f"/></p><p><img