The following table shows the progress o a given project at day 47 Duration Budget Cost Completed 1-2: Contact lo 250 450 380 100 2-3: Solieit 2-4: Design 4-3: Evaluate 12 0 18 350 100 3-5: Shoot 405 70 5-6: Place 16 (a) Draw the network diagram for this project, and determine slack times (b) Determine if the project is in control based on the time and cost to datÄ™ (USE PERFORMANCE INDICES). If not, what is the.cost overage or underage?
Expert Answer
(a) Network disgaram is as follows
https://d2vlcm61l7u1fs.cloudfront.net/media%2F4da%2F4dac95a3-0e3a-4171-ab1a-5aa5467554c1%2FphpCkfpjU.png
There are two alternative paths through the network as listed below.
1-2-3-5-6