The activities, predecessors, and time estimates of an insurance claim are given below. Assume that the activity times are independent.

Activity Predecessor Duration
A — 9
B — 13
C A , B 5
D A 11
E B, C, D 5
a.) The critical path is?

b.) The expected project completion time is?

c.) The earliest starting time of activity C is?

d.) The latest starting time of activity C is?

e.) What activity would you crash if you had to shorten the project by one day?

f.) The stack time associated with activity B is?

Expert Answer


Answer (a)

Critical path – The network path of highest lead time is known as critical path.
In this network diagram, there are three paths are