Sox Engineering designs and constructs air conditioning and heating (HVAC) systems for hospitals and clinics. Currently the company’s staff is overloaded with design work. There is a major design project due in 7 weeks. The penalty for completing the design late is $15,000 per week, since any delay will cause the facility to open later than anticipated, and cost the client significant revenue. If the company uses its inside engineers to complete the design, it will have to pay them overtime for all work. Sox has estimated that it will cost $10,000 per week (wages and overhead), including late weeks,