A small project is composed of seven activities whose timeestimates are listed in the following table:

Estimated Duration (weeks)

Beginning Node

Ending Node

Optimistic

Most Likely

Pessimistic

1

2

1

1

7

1

3

1

4

7

1

4

2

7

9

5

1

1

1

3

5

2

2

14

4

6

2

6

10

5

6

3

3

15

Using the classic PERT model, what is the probability that theproject will be completed two weeks earlier than its expectedduration?