A shop works a 400-minute day. The manager of the shop wants an output of 200 units per day for the assembly line that has the elemental tasks shown in the table. Do the following: Immediate Predecessor Task Time (minutes) 0.5 1.4 1.2 0.7 0.5 1.0 0.4 0.3 0.5 0.8 0.9 0.3 Task b,c h, j b. Assign tasks according to the most following tasks rule. Use greatest positional weight as a tiebreaker. Work Station Following Tasks (Click to select) (Click to select) (Click to select) (Click to select) (Click to select)