(Answered) : Ross Hopkins President Hopkins Hospitality Developed Tasks Durations Predecessor Relations Q33349316

Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels. Time (weeks) Immediate Time (weeks) Immediate Activity a mb Predecessor(sActivity a b Predecessor(s) C, E 24 18 14 5 14 D, G, H 20 C, E a) The expected (estimated) time for activity C is b) The variance for activity C is c) Based on the calculation of the estimated times, the critical path is (1) d) The estimated time for the critical path is e) The activity variance along the critical path is f) The probability 