Reliable Garage is completing production of the J2000 kit car.The following data are available for the? project:

????????????????????????????????????????????????????????????????????????????????????????????????????????  

Activity

Activity Time

?(dayday?s)

Immediate? Predecessor(s)

A

55

minus?

B

77

A

C

22

B

D

1010

C

E

44

C

F

44

C

G

33

F

H

44

?D, E, G

The critical path is A-B-C-D-H and the project duration is 28day?(s).

?(Enter your response as a whole? number.)

c. What is the slack for each? activity?

Activity

Activity

Time

?(dayday?s)

Slack

?(dayday?s)

A

55

nothing

B

77

nothing

C

22

nothing

D

1010

nothing

E

44

nothing

F

44

nothing

G

33

nothing

H

44

nothing