After reading the below give a brief summary or reply concerningthe risks associated with leveling resources, compressing orcrashing projects, and imposed durations or “catch-up” as theproject is being implemented?
The risks associated with leveling resources, compressingprojects, and imposed duration when projects are being implementedare a loss in flexibility and all activities will become critical.Reduced flexibility occurs from reduced slack in a project.Leveling is techniques used to examine a project for an unbalanceduse of resources, and for resolving resource over allocations.Compressing is the shortening of an activity or project. Often arisk is time overrun and an activity may have to be eliminated.Imposed