QUESTION S 5 points A multiple channel system has customers arriving at an average rate of five per hour and an average service time of forty minutes. The minimum number of servers for this system to be under loaded is: 0 a, 2 O e. None of these

Expert Answer


ANSWER: c. 4

Arrival rate, λ = 5 per hour

Service rate, μ = 60/40 = 1.5 customers per hour by each server

System utilization = λ/cμ = 5/(1.5c)

For system to be under loaded, utilization should be less than 1.

5/(1.5c) = 1, c = 5/1.5 = 3.33 . Server cannot be in

OR

PayPal Gateway not configured

OR

PayPal Gateway not configured

Leave a Reply

Your email address will not be published. Required fields are marked *

Related Post

(Solved) : Assume Following Variable Declarations Int X 13 Y 7 Z 8 Double U 40 Result Value Result St Q35107729 . . . .(Solved) : Assume Following Variable Declarations Int X 13 Y 7 Z 8 Double U 40 Result Value Result St Q35107729 . . . .

<br/><img src="https://media.cheggcdn.com/media%2F99e%2F99ebcd2b-e744-4a51-a3cd-230dfc94b382%2Fimage.png" alt="Assume the following variable declarations: int x 13, y 7, z 8; double u 4.0, result; What will be the value of result after" aria-describedby="d3f"/>Assume the following variable